Stoke on Trent District Heating – Priority Works 32 Updates

Morrison Utility Connections – District Heating have been engaged by Stoke on Trent City Council to design and build of this priority section of District Heating Network. The works are to be designed to provide an example of ‘Best Practice’ in the District Heating sector which have been designed to minimize the effects on the highway whilst provide an efficient and reliable source of renewable energy.

Morrison Utility Connections are acting as Principal Contractor with full responsibility for the safe and efficient delivery of the scheme.

Project Timetable
Start Date: October 2017
End Date: December 2017
Project Details
Location

The route of our works is along a 750m length of Leek Road with the junction of Glebe Street and Boughey Road.

Nature of Project

Morrison Utility Connections – District Heating have been engaged by Stoke City Council to design and build of this priority section of District Heating Network. The works are to be designed to provide an example of ‘Best Practice’ in the District Heating sector which have been designed to minimize the effects on the highway whilst provide an efficient and reliable source of renewable energy.

Morrison Utility Connections are acting as Principal Contractor with full responsibility for the safe and efficient delivery of the scheme.

Community

We understand that the nature of this project and these works may well have an effect on local residents and businesses along the planned route and we plan to minimise any disruption wherever possible.

Where temporary traffic management is required we will apply the appropriate measures to match the site situation and inform the local community by the most pertinent method.

We are committed to providing you with timely information and responding effectively to questions from local people so that any associated disruption can be minimised.

Contact info

Freephone number 0800 307 7995 (available 24/7)

Email address Projects4022@morrisonus.com

 

Whilst we are working in your local area, if you have any questions our on-site project supervisor will be happy to help, so please feel free to ask. Please remember when approaching the site team, that the signage and barriers are there for your safety – please don’t move barriers or signage or enter the work area under any circumstances.

Our project supervisor will be contacting local residents and stakeholders directly as our work progresses along their Road/Street/Avenue to inform residents of our intended works and to understand residents’ individual access requirements.

Project Updates

Friday 31st August 2018 10:28

Leek Road - All works completed.

Glebe Street - All works completed.

Ashford Street - Works recommenced after design approval by Stoke City Council and we are excavating the trench for pipework installation next week.

Friday 17th August 2018 15:44

Glebe Street/Station Road/Leek Road junction
The works here are well advanced and on time. We have now completed the remaining joints and connected the full system through. Over the coming week, the works will concentrate on backfilling and reinstating to a completion date before September. The road crossing to serve the 6th Form College has been undertaken over a period of nightshifts and we expect to complete these over the course of the next two weeks.

Ashford Street
Having recently encountered further complications, we are now finalising a design which should see the works recommence next week.

Additional Work:
We will be starting additional works outside the post office to install a new access chamber. The works are not expected to require restrictions to traffic flows.

Friday 10th August 2018 11:02

Ashford Street.-

Excavating the trench from Guilford Street to Crowther Street.

South Side of Station Road

Excavated trench and welding in specials.

6th Form College

Working night shifts to complete the road crossing near 4 way traffic lights.

Squires View

All works complete.

Friday 3rd August 2018 15:53

Works have recommenced on the junction with Glebe Street, Station Road and Leek Road to complete a small section of pipework required to close the first section. Works are on schedule and are expected to be complete with 3-4 weeks.

Ashford Street – works have progressed along with the initial 75m from Boughey Road now complete and re-opened to public use. We would thank everyone for their patience whilst this difficult section was constructed.
Works are continuing further along with the next section of road expected to be completed by the end of next week.

Friday 27th July 2018 14:58

Ashford Street – Works currently suspended pending updated design due to unforeseen underground obstructions.

Squires View – All pipework completed and only reinstatement works left to complete.

Station Road South – Works commencing Monday 30th July for five weeks.

Friday 20th July 2018 11:36

All sections are on programme as follows;

Ashford Street
Now reinstated up to and just past Watford Street.
Starting excavations on next section from Guilford Street towards College Road.

Squires View
Welding complete and this section will be reinstated by 27th July.

Friday 13th July 2018 13:06

Squires View – Works continuing and estimated to be completed by the end of July. Awaiting Design Approval for new pump station from client.
Ashford Street – Works continuing and on programme for completion by the end of October.

Friday 6th July 2018 13:52

Squires View – Works continuing and estimated to be completed by the end of July.
Ashford Street – Works continuing and estimated to be completed by the end of October.
Station Road (South Side) – Works planned to start on 23rd July - estimated duration 5 weeks.

Friday 29th June 2018 15:31

Ashford Street – Progressing with the excavation of the trench and pipe laying.
Squires View – Excavating the trench and pipe laying up to the temporary pump house.

Friday 22nd June 2018 13:06

Our compound has now moved from its home of the last 10 months off Lichfield Street which will stop the construction traffic seen during the works stop.

Works to Ashford Street that have been waiting on difficult design approvals have now been determined and the works will start again on Monday 25th June.

Works along Boughey Road are now complete.

Works to the junction of Glebe Street, Station Road and Leek Road have been reinstated whilst a final design is sorted for the south side of the junction. We are hopeful that this can be concluded within the near future and the works finished off thereafter.

Friday 15th June 2018 14:13

Station Road junction (North side) was completed on Tuesday 12th June and all traffic management has been removed.

Moving our compound from Lichfield Road to Squires View.

Ashford Street is still on stop awaiting agreement with client on how to proceed.

Friday 25th May 2018 11:21

Boughey Road junction with Ashford Street – Excavation complete installing pipework Tuesday 29th May.

Station Road North Side – Pipework complete. Reinstatement to be completed next week.

Ashford Street – Works still on hold pending instruction from Client.

Friday 18th May 2018 13:14

Boughey Road junction with Leek Road – Completed reinstatement and handed back to Highways

Boughey Road junction with Ashford Street – Excavating to install vent and drains.

Station Road North – Installing pipework, estimated completion date 31st May

Ashford Street – Works still on hold pending instructions from the Client.

Friday 11th May 2018 10:03

We have reduced our manpower on the project to one team whilst we await the client’s instructions on outstanding sections.

Ashford Street - Works suspended pending a decision off the client on how to proceed.
Boughey Road – Carriageway permanently reinstated. Just some block paviours to complete in the footway, we expect to be complete by Tuesday 15th.
Station Road / Glebe Street / Leek Road – We are working night shifts only, so we can accommodate the University’s requirements to reduce noise levels during this month’s exams.
We are excavating the trench at the moment.
Station Road crossing is now 80% permanently reinstated.

Friday 4th May 2018 13:02

Currently we are running with a reduced workforce whilst the re-design work required to accommodate the unforeseen underground obstructions is completed and some of these works will be on night shifts.

Ashford Street – Works suspended pending clearance to proceed by the client.
Boughey Road – Pipework complete and the road will be reinstated today.
Station Road - (Glebe Street, Leek Road junction) – South side - waiting for final design.
Road crossing is complete except for final reinstatement which will be completed next week.
North side- the trench is being altered / re-excavated to accommodate a new design due to unforeseen underground obstructions.
At present all installation works are programmed to be complete by mid-July (except for the commissioning phase).

Friday 27th April 2018 12:38

We have now encountered obstacles in the carriageway that will a redesign of our works to accommodate them, so in the meantime we are completing all available existing works as follows;

Boughey Road – Completing the last welds today and we plan to complete all reinstatement by next Friday.
Leek Road – Works suspended pending design changes.
Ashford Street – Works suspended pending design changes.

Friday 13th April 2018 16:38

Ashford Street
On programme and will have approximately 110m installed and reinstated by next week.
This section is highly congested with underground utilities and our trench is on average 3m deep.

Boughey Road
Last 15m left to complete, again a very congested area with the ground saturated with ground water which makes temporary trench support and pipe installation very difficult.

Station Road Crossing
We are crossing a major four way junction during night shifts, starting at 9pm and finishing at 5am with the use of a road closure. Junction is approximately 24m wide and trench is 2.2m deep and is protected by specifically designed road plates plus 20m of footpath will be exposed at the same depth to install 2 x 500mm steel insulated pipes.

Friday 6th April 2018 16:26

Glebe Street/ Station Road/Leek Road junction works

Works are progressing on nights shifts and were undertaken throughout the recent Bank Holiday period to reduce the impact on the road network. Despite encountering many services, we have progressed well and expect works to be completed within the next 2 weeks.

Next week the works will move onto the 6th Form pedestrian crossing, access will be maintained throughout.

The works will continue to connect the section in front of the Post Office through the junction.

Boughey Road:
Works are substantially complete with the final section currently being piped through. The section is now being backfilled and reinstated and traffic management is expected to be removed from the highway next week.

Ashford Street:
These works are continuing to progress with the works being redesigned to avoid the many services to adjacent properties.

Friday 23rd February 2018 15:47

Leek Road:

Working on two sections. The first is towards the Squires View area where we are well advanced with road crossing into the new development area. Works are in line to be completed next week where the traffic management can then be removed.

Outside the Post Office has seen the works move into the highway requiing complex traffic management and witnessing some delays around the junction. The works are being progressed with urgency and an understanding of the difficulties road users are facing. To mitigate delays we are working around the clock to progress and move from the area.

Boughey Road.

Works continue to work at both ends of the road. Works to the Leek Road end are progressing following complications with unknown services. The design of the scheme has been adjusted to maintain progress. The works on the Junction with Ashford Street are now entering the reinstatement phase so we would expect to be off the junction by the end of next week.

Ashford Street
The works are now progressing along. Further investigation of along the street will be undertaken in advance of the main works to minimise future complications and reduce the time we expect to be working along the street.

Friday 9th February 2018 15:53

Leek Road – We continue to work in several locations along Leek Road.
Outside 6th form college – these works have now been completed down to Squires View and the roads, footpath and bus stops are fully opened back to the public. A small area remains cordoned off for when the works recommence 16th February.
Outside the Post Office, the initial works have now been completed and the traffic management amended to reflect the advance of the works.


Boughey Road – We continue to work in two areas.
Leek Road end - The works are continuing with operations moving into the small cut through reducing the impact on the road.
Ashford Street junction – These works are progressing with complex ground conditions and utilities requiring significant adjustments to the design. However we are expecting substantial sections to be completed by the middle of next week.

Ashford Street – The works are progressing along the initial section as route exploratory works are being undertaken.

Friday 2nd February 2018 13:04

Leek Road – We continue to work in several locations along Leek Road.
Outside 6th form college – these works have now been completed down to Squires View and the roads, footpath and bus stops are fully opened back to the public. A small area remains cordoned off for when the works recommence 16th February.
Outside the Post Office, the initial works have now been completed and the traffic management amended to reflect the advance of the works.


Boughey Road – We continue to work in two areas.
Leek Road end - The works are continuing with operations moving into the small cut through reducing the impact on the road.
Ashford Street junction – These works are progressing with complex ground conditions and utilities requiring significant adjustments to the design. However we are expecting substantial sections to be completed by the middle of next week.

Ashford Street – The works are progressing along the initial section as route exploratory works are being undertaken.

Friday 26th January 2018 14:15

Leek Road
Works completed up to the Glebe street , Station Road Junction. The bus stops have now been reopened for public use.
Works outside the Post Office have now been completed and advanced further towards Boughey Road.
Traffic management have been changed to reflect these progressions.

Boughey Road:
Works progress along both ends of the street.
Complex undertakings around utilities are ongoing as the works turn into Ashford Street which are requiring redesigns.
Works to the south end of Boughey Road are progressing and will shortly move off the carriageway.

Ashford Street
Works are starting to the Boughey Road end.

Friday 19th January 2018 10:38

Boughey Road – Works continue on both ends of the highway, good progress made as the pipes now move onto the northbound carriageway. Areas being backfilled and reinstated.
Leek Road – Outside the 6th form college, these are now being backfilled, reinstated and completed
Leek Road – Post office – works are now reinstated in advance of the next phase commencing in 2 weeks time.

Friday 12th January 2018 15:53

Works progressing to complete the surfacing and kerb works along Leek Road. Night works are to be undertaken next week in order to mitigate and minimise any disruption to the public.
Works in front the Post Office are looking to be reduced by the end of next as next phase of the works commences.

Boughey Road will see the final sections being undertaken in order to progress onto the next stage of the works.

Friday 5th January 2018 16:19

Following the Christmas shutdown we have now remobilised to site:

Leek Road – the works to the approach to the Glebe Street/Station Road junction have been completed to a stage where the traffic lights have been returned to there normal working conditions.
The remaining works are no being undertaken off the carriageway and where we need to go back onto the highway, we will be doing so over the nights and returning all lanes back for the morning.

The works in front of the Post Office have been progressed over the Christmas period and we are expecting them to be completed by next Monday. Following this, the works will head further along Leek Road and then pass onto Boughey Road.

The works along Boughey Road were closed off during the Christmas shutdown to minimise the effects during the holiday period. We are now starting to complete the works and place the permanent surfacing back.

Friday 15th December 2017 15:46

Boughey Road – Excavations works significantly complete with the majority of the pipe installed.
Works next week will concentrate on reinstating the length of the street and only small localised sections being retained for future connecting works.

Leek Road – Section in front of the Post Office have been excavated with pipe being installed over this weekend.
Next week we will concentrate on the installation of communication ducts and the reinstatement to allow the section to be opened up in advance of the Christmas shutdown on Saturday 23rd.
The section along Leek Road in front of the 6th Form College has had significant progress with all excavation works completed. Works are now concentrated on pipe installation and backfill prior to the Christmas shutdown.

Friday 8th December 2017 15:15

• Leek Road: working in two locations

a. Opposite the 6th Form College – works progressed substantially over the past week. Reinstatement undertaken and the length of traffic management has now been reduced.
b. Traffic lights at the junction with Glebe Road/Station Road are to be adjusted to accommodate the next phase.
c. Works have started and progressing well outside of the Post Office sorting office. Works are being undertaken on nights to minimise the disruption to this key facility at this time of the year

• Boughey Road is advancing well with section now being resurfaced and opened back up. Works are progressing in order to complete the majority of the road in advance of Christmas holidays.

Friday 1st December 2017 14:54

Leek Road – Good progress continues to be made with section now being reinstated and handed back to the public.
Leek Road – the works have progressed in front of the Post Office, we would apologise for any inconvenience this is posing to those needing access to this building
The unpopular use of a convoy system adopted on sections has now being removed as a more traditional traffic management arrangements with cones and continuous flow of traffic has been established
Boughey Road – These works are well advanced with section to be completed and returned to public use expected by the end of this weekend.

Friday 24th November 2017 12:14

Leek Road – Good progress with sections now reinstated and traffic management levels reduced.
Boughey Road – Works continuing with good progress made and some sections started to be backfilled.
Trial holes on night shifts now complete.
Further sections on Leek Road to be started following approvals on the traffic management options.

Friday 17th November 2017 10:39

Leek Road - Works continue with good progress made over the week and section being backfilled, reinstated and re-opened to the public. The current convoy system should be ending over the next week.
Leek Road - Night works for trial holes.
Boughey Road – Works making good progress in line with the programme.

Friday 10th November 2017 15:33

Works continue and extend along Boughey Road
Backfill and reinstate to the first section on Leek Road
Works extending further along Leek Road and working days & nights

Friday 3rd November 2017 09:51

Excavation and installation works continue along Leek Road.
Excavation and installation works due to commence on Boughey Road.
Night works for trial pits along Leek Road at junction of Glebe Road and Station Road.