Welcome to our latest project page, which has been designed to keep all interested parties and stakeholders fully informed that we have been contracted by Durham County Council to provide new essential infrastructure connections.  The works include excavating, laying cables, traffic management and associated infrastructure works in the locality. Part of these works will be completed in the highway, and unfortunately this may cause some delays and disruption.

The project timetable may be subject to change depending upon weather conditions and we plan to keep you fully informed of any changes due to circumstances out of our control, so please do regularly check back here for the latest updates.

Project Timetable

Project Timetable

  • Start Date: October 2016
  • End Date: August 2017

Project Details

  • Location:

    From Newton Park services (just off junction 59 of the A1 on the A167 Durham Road) to NPG Darlington North substation on Whessoe Road

  • Nature of the Project:

    Morrison Utility Connections have been contracted by Durham County Council to provide new essential infrastructure connections.  The works include excavating, laying cables, traffic management and associated infrastructure works in the locality. Part of these works will be completed in the highway, and unfortunately this may cause some delays and disruption.

  • Community:

    We understand that the nature of this project and these works may well have an effect on local residents and businesses along the planned route and we plan to minimise any disruption wherever possible.

    Where temporary traffic management is required we will apply the appropriate measures to match the site situation and inform the local community by the most pertinent method.

    We are committed to providing you with timely information and responding effectively to questions from local people so that any associated disruption can be minimised.

  • Contact Info:

    If you have any questions, queries or concerns regarding these works, then please contact us:

    • Free Phone 0800 088 7332 (available 24/7)

    • Email This email address is being protected from spambots. You need JavaScript enabled to view it.

Updates

23 updates

  • MUC Admin Friday, 17 March 2017 12:13 Comment Link

    Dig and lay team 1 progressing on Burtree Lane, Traffic Management - single lane closure in place.
    Dig and lay team 2 progressing on A167, footpath closed.
    Substation build progressing, construction of switch room and transformer walls.
    DCC (Durham County Council) highway works on A167 progressing, single lane closure.
    DCC (Durham County Council) service diversion/new service installation works progressing along A167 and within the main site.

  • MUC Admin Friday, 10 March 2017 11:35 Comment Link

    Dig and lay team 1 progressing on Burtree Lane.
    Dig and lay team 2 progressing on the A167 Durham Road.
    Traffic Management - Lane closure will be in place on the A167 leading away from the A1M junction from 14-03-17 for 7 days for dig and lay team 2.
    A167 and A1M HDD’s (Horizontal Directional Drill’s) completed.
    Aycliffe Forrest substation build progressing.
    Durham County Council highway works progressing on A167 at Newton Park services.
    Durham County Council new drainage and gas works have started along the A167.
    Durham County Council highway and service works progressing on main site.

  • MUC Admin Monday, 06 March 2017 15:31 Comment Link

    A167 HDD (Horizontal Directional drill) completed.
    Gang 1 - Duct installation - Burntree Lane ongoing – Traffic Management - two way lights single lane closure.
    Tarmac 80M of Burntree Lane completed.
    Gang 2 - Duct installation - Durham Road ongoing – no lights but closed footpath.
    Aycliffe Forrest substation build – ongoing
    A167 Newton Park – Traffic Management – highway works on going.
    Installation of new services and diversion on the main site ongoing.

  • MUC Admin Tuesday, 28 February 2017 09:36 Comment Link

    A167 HDD (Horizontal Directional Drill) ongoing.
    Brafferton Lane – Traffic Management - road closure completed.
    Burtree Lane – Traffic Management - single lane closure ongoing – dig and lay team 1 (reduced to two way lights).
    A167 Durham Road – Traffic Management - lane closure completed.
    Aycliffe Forrest substation build on going.
    A167 Newton Park – Traffic Management - highways works ongoing.
    Installation of new services, highways and diversions on main site ongoing.

  • MUC Admin Monday, 20 February 2017 09:17 Comment Link

    A1M HDD (Horizontal Directional Drill) complete, demobilisation of the area currently underway.
    A167 HDD (Horizontal Directional Drill) currently is being setup.
    Brafferton Lane – Traffic Management - road closure ongoing – dig and lay team 2 (estimated to be finished by this weekend)
    Burtree Lane – Traffic Management - single lane closure ongoing – dig and lay team 1 (3 way lights still in place, to be reduced to two way next week)
    A167 Durham Road – Traffic Management - lane closure still in place, taper to be reduced by 20-02-17 and works complete by 24-02-17.
    Aycliffe Forrest substation build on going.
    A167 Newton Park – Traffic Management - highways works ongoing, single lane closure.
    Installation of new services, highways and diversions on main site ongoing.

  • MUC Admin Friday, 10 February 2017 10:01 Comment Link

    A1M HDD (Horizontal Directional Drill) ongoing and estimated to complete next week, as we are on drill 6 of 7.
    Whessoe Road dig and lay works completed, highway reinstated, Traffic Management - 3 way lights removed.
    Dig and lay team 1 on Burtree Lane, Traffic Management - two way lights in place.
    Dig and lay team 2 on A167 Durham Road, approaching Burtree Lane, Traffic Management - Lane closure in place.
    Aycliffe Forrest Substation civil build ongoing, switch room base poured, transformer T1 blinded.
    Durham County Council highway and service diversions/new services install works on going. Traffic Management - They have a lane closure on the A167 south bound Newton Park services.
    Durham County Council main site works, installing surface water drainage.
    Traffic Management - The road closure for Brafferton Lane will be in place from 13-02-17 for 5 days.

  • MUC Admin Friday, 03 February 2017 09:52 Comment Link

    Dig and Lay team 1 on Burtree Lane, Traffic Management - 3 way lights in place on Burtree Lane, junction of Whessoe Road.
    Dig and lay team 1 completed Whessoe Road.
    Dig and Lay team 2 on A167, Traffic Management - single lane closure in place on A167 Durham Road near A1M junction 59.
    A1M HDD (Horizontal Directional Drill) ongoing, 3 drills completed.
    Aycliffe Forrest substation, switchroom slab ready to pour, excavating for T2 slab.

  • MUC Admin Thursday, 26 January 2017 10:30 Comment Link

    HDD (Horizontal Directional Drill) under A1M ongoing.
    Dig and lay ongoing on Whessoe Road/junction of Burtree Lane – We will look at completing Whessoe Road and continue down Burtree Lane next week. Traffic Management, 3 way lights to remain in place.
    Dig and lay ongoing on A167 Durham Road. There will be a lane closure to be put in place from next week.
    Substation civil construction works ongoing.

  • MUC Admin Monday, 23 January 2017 14:38 Comment Link

    Dig and lay commencing on Whessoe Road, 3 way lights in place on Whessoe Road and the junction of Burtree Lane. Whessoe Road is expected to be completed by 26-01-17.
    Dig and lay commencing on A167 Durham Road in the verge, Traffic Management will be put in place on the A167 to reduce the lanes leading up to Brafferton Lane.
    A road closure is to be put in place on Brafferton Lane for 5 days starting on 30-01-17; letter drops to be completed to inform the local residents of our works.
    Horizontal Directional Drill (HDD) contractor mobilised on 16-01-17, A1M HDD commencing and they have already crossed underneath the A1M.
    Substation civil contractor mobilised, substation civil works commencing.

  • MUC Admin Friday, 13 January 2017 09:41 Comment Link

    Whessoe Road closure works complete on 12-01-17, Traffic Management to be removed 13-01-17.
    The A1M HDD (Horizontal Directional Drill) settlement monitoring has begun.
    Pipe for A1M HDD delivered and welded in readiness for the HDD mobilisation on 16-01-17.
    Welfare setup for substation civil construction phase in readiness for mobilisation on 16-01-17.

    Next week’s activities.

    Single lane closure on Whessoe Road towards the junction of Burtree Lane from 16-01-17.
    Begin excavation and lay from the south side of the A1M HDD joint bay down the A167 in the verge initially.
    Substation civil construction works begin.
    A1M HDD works begin.

  • MUC Admin Friday, 06 January 2017 12:10 Comment Link

    Road closure in place on Whessoe Road.
    Excavation and lay works ongoing on Whessoe Road.
    On target to complete our works on Whessoe Road by 13th January 2017.

  • MUC Admin Tuesday, 20 December 2016 11:04 Comment Link

    Traffic Management on Whessoe Road has been removed for the Christmas period.
    There will be no more excavations on Whessoe Road this year, but they will be continued in the New Year.
    Please be aware that Whessoe Road will have a road closure in place on 3rd January 2017 for 10 days.

  • MUC Admin Friday, 16 December 2016 10:03 Comment Link

    Traffic Management on Whessoe Road removed for Christmas.
    No more excavations on Whessoe Road this year, to be continued after the New Year.
    Please be aware that Whessoe Road will have a road closure in place on 3rd January 2017 for 10 days.

  • MUC Admin Thursday, 08 December 2016 16:13 Comment Link

    Fully mobilised for our dig and lay operation.
    Commencing on Whessoe Road (next to Darlington North substation).
    Traffic Management in place on Whessoe Road as the road is down to one lane.
    Commenced excavations and duct installations.

  • MUC Admin Thursday, 01 December 2016 12:42 Comment Link

    We have established our site office, welfare accommodation and lay down area in preparation to accept deliveries of the materials and equipment required to commence the project.

  • MUC Admin Friday, 25 November 2016 14:02 Comment Link

    No works in progress this week.

  • MUC Admin Monday, 21 November 2016 15:23 Comment Link

    No works in progress this week.

  • MUC Admin Friday, 11 November 2016 10:41 Comment Link

    No works in progress this week.

  • MUC Admin Thursday, 03 November 2016 14:36 Comment Link

    Currently no works in progress.

  • MUC Admin Friday, 28 October 2016 08:08 Comment Link

    Trial holes and slip trenches work 100% completed.

  • MUC Admin Monday, 24 October 2016 12:35 Comment Link

    Ground Penetrating Radar Surveys (GPR) 100% completed.
    Trial holes and slip trenches work 75% completed.

  • MUC Admin Friday, 14 October 2016 07:11 Comment Link

    Trial holes and slip trenches work ongoing.
    Ground Penetrating Radar Surveys (GPR) ongoing.

  • MUC Admin Thursday, 13 October 2016 07:15 Comment Link

    Undertaking trial holes and slip trenches between Newton Park Services, A1 Junction 59 and Whessoe Road to establish service depths and positions.
    Ground Penetrating Radar Surveys (GPR) along the same route which has meant some traffic management has been needed.
    These initial works are scheduled to be complete by the end of October 2016.

back to top

Morrison Utility Connections is a trading name of and a business owned by Morrison Utility Services. Company No. 4530602. Registered office: Abel Smith House, Gunnels Wood Road, Stevenage, Hertfordshire, SG1 2ST. | Login


Warning: file_put_contents(/home/morrisuc/public_html/index.php): failed to open stream: Permission denied in /home/morrisuc/public_html/index.php(56) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code on line 15