Welcome to our latest project page, which has been designed to keep all interested parties and stakeholders fully informed that we have been contracted to carry out essential upgrading of the electricity network including all of the associated infrastructure works between Shopland Road, Rochford to Pippins Road, Burnham on Crouch.

The project timetable may be subject to change depending upon weather conditions and we plan to keep you fully informed of any changes due to circumstances out of our control, so please do regularly check back here for the latest updates.

Project Timetable

Project Timetable

  • Start Date: 21st March 2016
  • End Date: November 2016

Project Details

  • Location:

    Between Shopland Road, Rochford to Pippins Road, Burnham on Crouch

  • Nature of the Project:

    Morrison Utility Connections have been contracted to carry out essential upgrading of the electricity network including all of the associated infrastructure works.

  • Community:

    We understand that the nature of this project and these works may well have an affect on local residents and businesses along the planned route and we plan to minimise any disruption wherever possible.

    Where temporary traffic management is required we will apply the appropriate measures to match the site situation and inform the local community by the most pertinent method.

    We are committed to providing you with timely information and responding effectively to questions from local people so that any associated disruption can be minimised.

  • Contact Info:

    If you have any questions, queries or concerns regarding these works, then please contact us:

    • Free Phone 0800 088 7332 (available 24/7)

    • Email This email address is being protected from spambots. You need JavaScript enabled to view it.

Updates

40 updates

  • MUC Admin Monday, 19 December 2016 13:35 Comment Link

    Project completed.

  • MUC Admin Friday, 16 December 2016 10:05 Comment Link

    All works complete.
    Retaining a presence in Burnham on Crouch until the end of December whilst completing the Quality Assurance File.

  • MUC Admin Thursday, 08 December 2016 15:24 Comment Link

    All works complete.
    De-mobilisation complete.
    Retaining a presence in Burnham on Crouch until the end of December whilst completing the Quality Assurance File.

  • MUC Admin Friday, 02 December 2016 11:40 Comment Link

    De-mobilisation complete and retaining a presence in Burnham on Crouch until the end of December 2016.

  • MUC Admin Friday, 25 November 2016 14:03 Comment Link

    De-mobilisation continues until the end of November and whilst still retaining a presence in Burnham on Crouch until the end of December 2016.

  • MUC Admin Monday, 21 November 2016 15:32 Comment Link

    Continuing to de-mobilise until the end of November and whilst still retaining a presence in Burnham on Crouch until the end of December 2016.

  • MUC Admin Friday, 11 November 2016 10:38 Comment Link

    De-mobilisation continues until the end of November and whilst still retaining a presence in Burnham on Crouch until the end of December 2016.

  • MUC Admin Thursday, 03 November 2016 15:12 Comment Link

    Continuing to de-mobilise until the end of November and retaining a presence in Burnham on Crouch until the end of December 2016.

  • MUC Admin Friday, 28 October 2016 08:45 Comment Link

    All works complete.

  • MUC Admin Monday, 24 October 2016 13:25 Comment Link

    Substation snagging list still ongoing.
    Continuing the preparation and finalising QA file.

  • MUC Admin Friday, 14 October 2016 11:02 Comment Link

    Substation snagging list ongoing.
    Preparing and finalising QA file.

  • MUC Admin Friday, 07 October 2016 11:17 Comment Link

    Substation snagging list on going (expected to be completed next week).
    Preparing QA file for handover.

  • MUC Admin Friday, 07 October 2016 11:17 Comment Link

    Substation snagging list on going (expected to be completed next week).
    Preparing QA file for handover.

  • MUC Admin Friday, 30 September 2016 07:20 Comment Link

    Grid route energised.
    Snagging list complete.
    Land owner walkover south of River Crouch completed yesterday.
    Land owner walkover north of River Crouch will be completed 12:00 today.

  • MUC Admin Friday, 23 September 2016 08:36 Comment Link

    Substation works nearing completion.
    Snagging list 95% complete, preparing for final walk over with land owners next week to confirm 100% of snagging completed.
    Preparing QA files for handover.
    Preparing for energisation.

  • MUC Admin Friday, 16 September 2016 08:06 Comment Link

    Substation works still ongoing.
    Snagging list 95% complete.
    Preparing QA file for handover.
    Preparing for energisation.

  • MUC Admin Friday, 09 September 2016 08:27 Comment Link

    Substation works still ongoing.
    Snagging list 95% complete.
    Preparing QA file for handover.

  • MUC Admin Friday, 02 September 2016 11:03 Comment Link

    Substation works still ongoing.
    Snagging list nearing completion.
    As-built data sent.
    Preparing QA file for handover.

  • MUC Admin Wednesday, 31 August 2016 08:49 Comment Link

    Substation works still ongoing.
    Snagging list ongoing.
    Compiling paperwork and as-built data for handover.

  • MUC Admin Thursday, 18 August 2016 13:41 Comment Link

    Substation works still ongoing.
    Communication pits north of the River Crouch complete.
    Snagging list ongoing.

  • MUC Admin Friday, 12 August 2016 09:42 Comment Link

    Substation works still ongoing.
    Communication pits north of the River Crouch are now 90% complete.
    Snagging list still ongoing.
    All trenching works complete.

  • MUC Admin Friday, 05 August 2016 07:43 Comment Link

    Substation works still ongoing.
    Communication pits north of the River Crouch ongoing.
    Snagging list still ongoing.

  • MUC Admin Thursday, 28 July 2016 07:42 Comment Link

    Substation works still ongoing.
    Communication pits south of the River Crouch completed.
    Commencing communication pits north of the River Crouch next week.
    Snagging list still ongoing.
    Ducting work in the footway on Pippins Close completed.

  • MUC Admin Friday, 22 July 2016 12:42 Comment Link

    Substation works continue..
    Communication pits are being constructed and installed along the route.
    Snagging list ongoing.
    Commenced the last section of ducting in the footway on Pippins Close.

  • MUC Admin Thursday, 14 July 2016 14:05 Comment Link

    Trenching works are complete south of the River Crouch - Small snagging list started and a few small items remain.
    Trenching works north of the River Crouch have commenced and are progressing well.
    Last directional drill north of the River Crouch complete and now demobilised from site.
    Substation works still ongoing.

  • MUC Admin Friday, 08 July 2016 11:44 Comment Link

    Trenching works are complete south of the River Crouch (except for a small snagging list to complete).
    Trenching works North of River Crouch will commence on Monday.
    All current planned directional drilling works are completed, which leaves one remaining drill north of the River Crouch.
    Substation works ongoing.

  • MUC Admin Friday, 01 July 2016 14:36 Comment Link

    The extensive trenching sections and ducts through farmland continue.
    The UXO (unexploded ordinance) survey is now fully complete.
    Commenced the preparations for the next directional drill.
    The works for the new substation have now commenced.

  • MUC Admin Friday, 24 June 2016 12:29 Comment Link

    The demobilisation process for the directional drill at the River Crouch continues to progress well.
    The extensive trenching sections through farmland are progressing and will continue through to completion.

  • MUC Admin Friday, 17 June 2016 11:43 Comment Link

    Excavation works on Pippins Road are now completed.
    The directional drill under the River Crouch now completed, ducting pulled and the demobilisation process has started with the clean down process well underway.
    The trenching sections through farmland continue to progress well.

  • MUC Admin Thursday, 09 June 2016 13:46 Comment Link

    Excavation works continue on Pippins Road and we are about 90% completed.
    The directional drill under the River Crouch is still ongoing.
    Commenced civil's preparation work for trenching sections through farmland.

  • MUC Admin Friday, 03 June 2016 09:13 Comment Link

    Excavation works on Eastern Road have been completed and the road has been reinstated.
    Commenced excavation works on Pippins Road and we are about 50% completed.
    The directional drill under the River Crouch is still ongoing.

  • MUC Admin Friday, 27 May 2016 12:39 Comment Link

    Excavation works on Stambridge Road have been completed and the road has been reinstated.
    Excavation works on Devonshire Road have been completed and the road has been reinstated.
    Excavation works on Eastern Road are on schedule to be completed today.
    We have commenced the direction drill under the River Crouch.

  • MUC Admin Friday, 20 May 2016 12:36 Comment Link

    We have completed the excavation works on Station Road.
    Excavation works have commenced in Devonshire Road and we hope to be completed in Devonshire Road by Wednesday next week and then commence excavation works on Eastern Avenue.
    We are mobilising for the drill under the River Crouch.
    We have completed the drill under the River Roach.
    We will have completed the excavation works on Stambridge Road by the end of the weekend.
    We hope to have all ducting work complete within the next 2 weeks.

  • MUC Admin Friday, 13 May 2016 13:12 Comment Link

    Excavation works on Creeksea Ferry Road completed.
    Excavation works on Foundry Lane completed.
    Excavation works on Station Road (road crossing) completed.
    Excavation works on Stambridge Road ongoing and nearing completion.
    All access roads on schedule to be completed this weekend.
    Access road on Creeksea Ferry Road has been removed.
    Archaeology survey complete.
    UXO (unexploded ordinance) survey complete on the parts of the route we have access to.
    Planning to start works on Devonshire Road on Monday morning.

  • MUC Admin Thursday, 05 May 2016 14:22 Comment Link

    Excavation works progressing on Stambridge Road, Great Stambridge are slower than expected due to poor ground conditions.
    Excavation works progressing on Foundry Lane, Burnham on Crouch will hopefully completed this weekend.
    Excavation works in Creeksea Ferry Road have started and will be complete by mid May.
    The temporary road at Creeksea (next to the Parlour Cafe) is now complete.
    The temporary road at Creeksea Road is now complete.
    The UXO (unexploded ordinance) team have completed all of their survey.
    The directional drill under Pagelsham Creek is complete.
    Preparations for the directional drill under the River Crouch and River Roach are ongoing.

  • MUC Admin Friday, 29 April 2016 11:27 Comment Link

    Excavation works progressing on Stambridge Road, Great Stambridge are slower than expected due to poor ground conditions.
    Excavation works progressing on Foundry Lane, Burnham on Crouch will hopefully completed by next Friday.
    Excavation works in Creeksea Ferry Road have started and will be complete by mid May.
    The temporary road at Creeksea (next to the Parlour Cafe) is now approximately 90% complete.
    The UXO (unexploded ordinance) team have completed approximately 85% of their survey.

  • MUC Admin Friday, 22 April 2016 14:18 Comment Link

    The excavation works on Stambridge Road, Great Stambridge and on Foundry Lane, Burnham on Crouch are still ongoing.
    Commenced excavation works on Creeksea Ferry Road.
    The temporary road at Creeksea (next to the Parlour Cafe) is approximately 70% complete.
    The UXO (unexploded ordinance) team are continuing to search the route prior to any excavation work taking place.

  • MUC Admin Friday, 15 April 2016 10:57 Comment Link

    We are continuing the excavation work on Stambridge Road, Great Stambridge and this is taking slightly longer than anticipated due to the variations in the depth of the concrete of the type 4 road.
    We are continuing the excavation work on Foundry Lane, Burnham on Crouch.
    The first temporary road for the directional drill has been completed.
    We are now working on a temporary road at Creeksea next to the Parlour Cafe to give us access into the field at the rear.
    The UXO (unexploded ordinance) team are continuing to search the route prior to any excavation work taking place & they are now moving on to other farms ahead of the temporary road team.

  • MUC Admin Friday, 08 April 2016 09:27 Comment Link

    Commenced excavation work on Stambridge Road, Great Stambridge.
    Commenced excavation work on Foundry Lane, Burnham on Crouch.
    The first temporary road for the directional drill has been completed.
    The UXO (unexploded ordinance) team are continuing to search the route prior to any excavation work taking place.

  • MUC Admin Friday, 01 April 2016 14:39 Comment Link

    We have established our site office, welfare accommodation and warehouse in preparation to accept deliveries of the materials required to commence the project.

back to top

Morrison Utility Connections is a trading name of and a business owned by Morrison Utility Services. Company No. 4530602. Registered office: Abel Smith House, Gunnels Wood Road, Stevenage, Hertfordshire, SG1 2ST. | Login


Warning: file_put_contents(/home/morrisuc/public_html/index.php): failed to open stream: Permission denied in /home/morrisuc/public_html/index.php(56) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code(1) : eval()'d code on line 15